Great Britain · NESO TEC register

TEC register with history

The Transmission Entry Capacity (TEC) register lists projects with a contract to connect to the GB transmission network that are not built yet. NESO updates it regularly and replaces the previous file; we archive every version since 16 November 2026, and hold 54 editions back to 6 December 2024.

Contracted, not built
592 GW
Projects
1,799
Connection sites
789

Contracted capacity per connection site

Connection siteContracted MW
Alverdiscott 400kV Substation10.3 GW
Creyke Beck 400kV Substation7.6 GW
Grimsby West 400kV Substation6.6 GW
Trent Valley South Connection Node D 400kV Substation6.4 GW
Longside 400kV Substation5.5 GW
Necton 400kV Substation5.2 GW
Cheshire Connection Node A 400kV Substation5.1 GW
South Anglia Connection Node C 400kV Substation4.9 GW
Trent Valley South Connection Node B 400kV Substation4.9 GW
Trent Valley South Connection Node C 400kV Substation4.6 GW
Norwich Main 400kV Substation4.4 GW
Navenby 400kV Substation4.4 GW
Birkhill Wood 400kV Substation4.4 GW
Drax 400kV Substation4.3 GW
East Claydon 400kV Substation4.1 GW
Sussex and Romney Connection Node A 400kV Substation4.0 GW
Hawthorn Pit 400kV Substation3.8 GW
Teeside Connection Node B3.6 GW
High Marnham 400kV Substation3.6 GW
East Kent connection node A 400kV Substation3.5 GW
Branxton 400kV Substation3.5 GW
Greens 400kV Substation3.5 GW
Bodelwyddan 400kV Substation3.5 GW
Chickerell 400kV Substation3.5 GW
West Anglia Connection Node F 400kV Substation3.4 GW
Hurlie 400kV substation3.4 GW
Feckenham 400kV Substation3.4 GW
Shurton 400kV Substation3.3 GW
Banniskirk 400kV Substation3.3 GW
Blyth 400kV Substation3.2 GW
Daines 400kV Substation3.1 GW
Peterhead 400kV Substation3.1 GW
Biggleswade 400kV Substation3.1 GW
Eggborough 400kV Substation3.0 GW
North Anglia Connection Node B 400kV Substation3.0 GW
Cilfynydd 400kV Substation3.0 GW
Drakelow 400kV Substation3.0 GW
Nursling 400kV Substation3.0 GW
Walpole 400kV Substation2.9 GW
Near Branxton 400kV Substation2.9 GW
Kingsnorth 400kV Substation2.8 GW
Staffordshire Connection Node A 400kV Substation2.8 GW
Weston Marsh 400kV Substation2.7 GW
Thorpe Marsh 400kV Substation2.7 GW
Penwortham 400kV Substation2.7 GW
North Anglia Connection Node A 400kV2.5 GW
Trent Valley South Connection Node A 400kV2.5 GW
North Anglia Connection Node C 400kV Substation2.5 GW
Leeds North Connection Node C 400kV Substation2.4 GW
Teeside Connection Node 2 C 132/400kV Substation2.4 GW
Solent Connection Node C 400kV2.4 GW
North Anglia Connection Node E 400kV Substation2.4 GW
West Anglia Connection Node I 400kV substation2.3 GW
Derbyshire Connection Node A 400kV Substation2.3 GW
Northern Shetland 400kV Substation2.3 GW
Coddington 400kV Substation2.2 GW
Carrington 400KV Substation2.1 GW
Cottam 400kV Substation2.1 GW
Enderby 400kV Substation2.1 GW
Market Harborough 400kV Substation2.1 GW
West Anglia Connection Node C 400kV Substation2.1 GW
Derbyshire Connection Node G 400kV2.0 GW
Swansea North 400kV Substation2.0 GW
Gallos 66kv Offshore Substation2.0 GW
West Anglia Connection Node H 400kVSubstation2.0 GW
Machair 275/66kV Offshore Substation2.0 GW
Dunstable 400kV Substation1.9 GW
Melksham 400kV Substation1.9 GW
West Anglia Connection Node G 400kV Substation1.9 GW
Tealing 400kV Substation1.9 GW
Harker 400kV Substation1.8 GW
South Wales West Connection Node A 400kV Substation1.8 GW
Basingstoke East 400kV Substation1.8 GW
Lackenby 400kV Substation1.8 GW
Earba PSH Powerhouse Substation1.8 GW
Glen Earrach PSH 400kV substation1.8 GW
Wearside Connection Node B 400kV Substation1.8 GW
Thornton 400kV Substation1.8 GW
Legacy 400kV Substation1.7 GW
New Dounreay 400kV substation1.7 GW
Monk Fryston 400kV Substation1.7 GW
North Humber Connection Node E 400kV Substation1.7 GW
Ferrybridge C 275kV Substation1.7 GW
Langage 400kV Substation1.6 GW
Staythorpe 400kV Substation1.6 GW
Woolavington 400kV Substation1.6 GW
Norton East 400kV Substation1.6 GW
West Anglia Connection Node A 400kV Substation1.6 GW
West Anglia Connection Node D 400kV Substation1.6 GW
Cheshire Connection Node A2 400kV1.6 GW
Eaton Socon 400kV Substation1.5 GW
Rayleigh 400kV Substation1.5 GW
South Anglia Connection Node E 400kV Substation1.5 GW
Bolney 400kV Substation1.5 GW
Chiltern Connection Node C 400kV Substation1.5 GW
Lincolnshire Coastal Node 400kV Substation1.5 GW
Fearna Pump Storage Hydro 2 400/15kV Substation1.5 GW
Trent Valley North Connection Node B 400kV Substation1.5 GW
Leeds North Connection Node B 400kV Substation1.4 GW
Sussex and Romney Connection Node B 400kV Substation1.4 GW
South Anglia Connection Node B 400kV Substation1.4 GW
Cellarhead 400kV Substation1.4 GW
New North East Substation 400kV Substation1.4 GW
Imperial Park B 400kV Substation1.4 GW
Arnish Lewis Hub 400kV Substation1.4 GW
Butlers Wood 400kV Substation1.4 GW
East Kent Connection Node B 400kV Substation1.4 GW
Cockenzie 400/275kV1.3 GW
Severn Connection Node A 400kv Substation1.3 GW
East Anglia Project Three Offshore Platform1.3 GW
Imw01 Offshore 275/66kv Offshore Substation1.3 GW
Ironbridge 400kV Substation1.3 GW
Fiddlers Ferry 275kV Substation1.3 GW
Coire Glas GSP1.3 GW
Pont Abraham GSP1.3 GW
North Kent Connection Node A 400kV Substation1.3 GW
Botley West 400kV Substation1.3 GW
Mablethorpe 400kV Substation1.3 GW
North Wales connection Node A 400kV Substation1.3 GW
West Anglia Connection Node B 400kv Substation1.2 GW
Pembroke 400kV Substation1.2 GW
Kincardine North 400kV Substation1.2 GW
South Anglia Connection Node A 400kV Substation1.2 GW
South Humber Connection Node A 400kV1.2 GW
Teeside Connection Node A 400kV Substation1.2 GW
Warley 275kV Substation1.2 GW
Connah's Quay 400kV Substation1.2 GW
Lancashire Connection Node B 400kV Substation1.2 GW
Westfield 132/33kV1.2 GW
Exeter 400kV Substation1.2 GW
New Deer 2 400kV Substation1.2 GW
Branxton 400/132kV1.2 GW
Bramford 400kV Substation1.2 GW
Cowley 400kV Substation1.2 GW
Sundon 400kV Substation1.2 GW
Alyth 400kV Substation1.1 GW
Bicker Fen 400kV Substation1.1 GW
Braintree 400kV Substation1.1 GW
Warwickshire Connection Node A 400kV Substation1.1 GW
Wearside Connection Node A 275kV Substation1.1 GW
Derbyshire Connection Node B 400kV Substation1.1 GW
Pentir 400kV Substation1.1 GW
Rhigos 400kV Substation1.1 GW
Five Estuaries 220/66 kV Offshore Substation1.1 GW
Wylfa South 400kV Substation1.1 GW
Hams Hall 400kV Substation1.1 GW
Ninfield 400kV Substation1.1 GW
Jubilee Farm 275kV Substation1.0 GW
Killingholme 400kV Substation1.0 GW
Mererid Offshore Wind Farm 220/32kv Substation1.0 GW

Largest 150 of 789 sites shown. Projects with status "Built" are excluded. Source: NESO TEC register, as published.

The register over time

Contracted capacity went from 538 GW in December 2024 to 592 GW now, across 54 editions. Older editions were recovered from archived copies.

6 Dec 2024 · 538 GW · 1,632 projects18 Nov 2026 · 592 GW · 1,799 projects

Changes since the previous version

No change between the two most recent daily versions. New, removed and resized projects appear here, and on the data status page, as soon as NESO publishes a new file.

Great Britain

Get TEC register changes by email

Pick connection sites or technologies. We'll tell you when projects are added, removed or delayed.